PSALM starts third round of bidding for Manila Thermal plant

03 Oct 2007

The Power Sector Assets and Liabilities Management Corporation (PSALM) has officially opened the third round of bidding for the decommissioned or retired Manila Thermal Power Plant (MTPP) located at Isla de Provisor in Paco, Manila, as it takes advantage of the positive feedback from investors on the government's privatization program.

In an Invitation to Bid (ITB) published in three newspapers starting Wednesday, 03 October, PSALM indicated that the MTPP would be sold on an "as is, where is" basis, which would include the plant equipment, auxiliaries and accessories as well as the underlying land.

PSALM hopes to attract more investors in the MTPP auction by including the land in the sale. The two-hectare land is located in a prime area, being near SM Manila and other commercial centers. The size of the land is ideal for industrial purposes.

The ITB, which will be published until Friday, 05 October, stated that PSALM would be accepting Letters of Interest (LOI) from prospective investors until 16 October 2007. In addition to the submission of the LOI, interested parties will be required to execute a Confidentiality Agreement and an Undertaking, and pay a non-refundable fee of USD500 not later 18 October 2007. Investor groups meeting these requirements will be issued the Bidding Package for the MTPP.

The Pre-bid Conference for the MTPP is set on 24 October, while the bidding will be held on 19 December at PSALM's Makati City office.

Since the plant is already retired, PSALM expects bidders engaged in the construction or steel manufacturing business, or those eyeing the scrap value of the MTPP's equipment, component auxiliaries and accessories, to participate in the bidding for the decommissioned facility.

Located in Ermita along the Pasig River, the MTPP has two identical generating units, each with a capacity of 100 megawatts (MW). Unit One was commissioned on 01 September 1965, while Unit Two was commissioned on 15 October 1966. Both units substantially contributed power to the Luzon Grid until they were retired in January 2000. All plant systems are intact and all major equipment properly maintained and preserved.

The first two biddings for the MTPP - held in the first quarter of 2005 and the last quarter of 2006 - failed primarily due to lack of investor interest. On the off chance that the December bidding will again fail, PSALM may resort to conducting a third party auction for the decommissioned plant. This means PSALM will tap a third party auctioneer that will provide a comprehensive asset disposal service to the Corporation. This will involve formulating an appropriate sale strategy and methodology for the MTPP and the other retired power plants for sale. This includes the administration of an inventory of the assets, the preparation of the assets, the strategic conduct of the auction, and the removal of the assets from their respective sites.

Strategic Communications and Partnership Division